[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900014":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},900014,582,2,"多选题","（2019年考题）下列入工、材料、机械台班的消耗，应计入定额消耗量的有（ ）。 A.准备与结束工作时间 B.施工本身原因造成的工人停工时间 C.措施性材料的合理消耗量D不可避免的施工废料 E.低负荷下的机械工作时间",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":16},"B",false,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":16},"E","ACD","B错，施工本身原因造成的工人停工时间，属于损失时间，不计入定额；E错，低负荷下的机械工作时间，属于损失时间，不计入定额时间。",{"id":6,"name":26,"category":27,"favorite":28},"建设工程计价","建筑工程",0]