[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900012":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900012,582,2,"多选题","（2016年考题）下列定额测定方法中，主要用于测定材料净用量的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","现场技术测定法",false,{"key":16,"text":17,"correct":18},"B","实验室试验法",true,{"key":20,"text":21,"correct":14},"C","现场统计法",{"key":23,"text":24,"correct":18},"D","理论计算法",{"key":26,"text":27,"correct":14},"E","写实记录法","BD","本题考查的是确定材料定额消耗量的基本方法。选项A主要用于确定材料损耗量；选项C不能作为确定材料净用量定额和材料损耗定额的依据，只能作为编制定额的辅助性方法使用；选项E是计时观察法的一种。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]