[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900009":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900009,582,2,"多选题","（2020年真题）关于其他项目清单与计价表的编制，下列说法正确的有（）.",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","材料暂估单价进入清单项目综合单价，不汇总到其他项目清单计价表总额",true,{"key":16,"text":17,"correct":18},"B","暂列金额归招标人所有，投标人应将其扣除后再做投标报价",false,{"key":20,"text":21,"correct":14},"C","专业工程暂估价的费用构成类别应与分部分项工程综合单价的构成保持一致",{"key":23,"text":24,"correct":18},"D","计日工的名称和数量应由投标人填写",{"key":26,"text":27,"correct":18},"E","总承包服务费的内容和金额应由投标人填写","AC","P48-51 A选项：材料（工程设备〉暂估单价进入清单项目综合单价，此处（其他项目清单与计价汇总表）不汇总。A正确 B选项：此表（暂列金额明细表）由招标人填写，如不能详列，也可只列暂定金额总额，投标人应将上述暂列金额计入投标总价中.B错误 C选项：专业工程的暂估价一般应是综合暂估价，包括人工费、材料费、施工机具使用费、企业管理费和利润，不包括规费和税金。C正确 D选项：此表（计日工表）项目名称、暂定数量由招标人填写，D错误 E选项：此表（总承包服务费计价表）项目名称、服务内容由招标人填写。E错误",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]