[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900006":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900006,582,2,"多选题","（2015年考题）为了便于措施项目费的确定和调整，通常采用分部分项工程量清单方式编制的措施项目有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","脚手架工程",true,{"key":16,"text":17,"correct":14},"B","垂直运输工程",{"key":19,"text":20,"correct":21},"C","二次搬运工程",false,{"key":23,"text":24,"correct":21},"D","已完工程及设备保护",{"key":26,"text":27,"correct":14},"E","施工排水降水","ABE","措施项目中可以计算工程量的项目清单宜采用分部分项工程量清单的方式编制。包括脚手架工程，混凝土模板及支架（撑），垂直运输、超高施工增加，大型机械设备进出场及安拆，施工排水、降水等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]