[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900002":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},900002,582,2,"多选题","（2019年考题）在工程量清单编制中，施工组织设计、施工范围和验收规范可以用于确定（ ）。 A.项目名称B项目编码C项目特征 D.计量单位 E.工程数量",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":16},"B",false,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":16},"D",{"key":22,"text":22,"correct":13},"E","ACE","施工组织设计、施工规范、验收规范，可以确定项目名称、项目特征、工程量。项目编码和计量单位，是工程量清单计价和计量规范可以确定的。",{"id":6,"name":26,"category":27,"favorite":28},"建设工程计价","建筑工程",0]