[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900001":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900001,582,2,"多选题","（2019年考题）关于分部分项工程项目清单的编制，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目编码第7-9位为分项工程项目名称顺序码",true,{"key":16,"text":17,"correct":18},"B","项目名称应按工程量计算规范附录中给定的名称确定",false,{"key":20,"text":21,"correct":18},"C","项目特征应按工程量计算规范附录中规定的项目特征予以描述",{"key":23,"text":24,"correct":14},"D","计量单位应按工程量计算规范附录中给定的，选用最适宜表现项国特征并方便计量的单位",{"key":26,"text":27,"correct":18},"E","工程量位按实际完成的工程量计算","AD","B错，项目名称应按各专业工程工程量计算规范附录的项目名称结合拟建工程的实际确定；C错，项目特征应按各专业工程工程量计算规范附录中规定的项目特征，结合技术规范、标准图集、施工图纸，按照工程结构、使用材质及规格或安装位置等，予以详细而准确的表述和说明；E错，工程量应以实体工程量计算，并以完成后的净值计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]