[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899998":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899998,582,2,"多选题","（2018年考题）关于工程量清单计价的基本程序和方法，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单位工程造价通过直接费、间接费、利润汇总",false,{"key":16,"text":17,"correct":18},"B","计价过程包括工程量清单的编制和应用两个阶段",true,{"key":20,"text":21,"correct":14},"C","项目特征和计量单位的确定与施工组织设计无关",{"key":23,"text":24,"correct":18},"D","招标文件中划分的由投标人承担的风险费用纳入综合单价中",{"key":26,"text":27,"correct":14},"E","工程量清单计价活动伴随竣工结算而结束","BD","工程量清单计价的基本程序。选项A错误，单位工程造价=分部分项工程费+措施项目费+其他项目费+规费+税金；选项B正确，工程量清单计价的过程可以分为两个阶段，即工程量清单的编制和工程量清单的应用两个阶段；选项C错误，确定项目特征与施工组织设计有关；选项D正确，风险费用是隐含于已标价工程量清单综合单价中；选项E错误，工程量清单计价活动涵盖施工招标、合同管理以及竣工交付全过程，主要包括：编制招标工程量清单、招标控制价、投标报价，确定合同价，进行工程计量与价款支付、合同价款的调整、工程结算和工程计价纠纷处理等活动。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]