[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899986":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899986,582,2,"多选题","（2018年考题）按照费用构成要素划分的建筑安装工程费用项目组成规定，下列费用项目应列入材料费的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","周转材料的摊销，租赁费用",true,{"key":16,"text":17,"correct":14},"B","材料运输损耗费用",{"key":19,"text":20,"correct":21},"C","施工企业对材料进行一般鉴定，检查发生的费用",false,{"key":23,"text":24,"correct":21},"D","材料运杂费中的增值税进项税额",{"key":26,"text":27,"correct":14},"E","材料采购及保管费用","ABE","选项C错误，施工企业对材料进行一般鉴定，检查发生的费用是企业管理费。选项D错误，不包括材料运杂费中的增值税进项税额。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]