[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899964":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899964,582,2,"多选题","在新增资产固定资产价值的确定过程中，建设单位管理通常按照下列（ ）总额按比例计算。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建筑工程",true,{"key":16,"text":17,"correct":14},"B","安装工程",{"key":19,"text":20,"correct":14},"C","需安装设备价值总额",{"key":22,"text":23,"correct":24},"D","不需安装设备价值总额",false,{"key":26,"text":27,"correct":24},"E","设备购置费总额","ABC","2020版教材P308 一般情况下，建设单位管理费按建筑工程、安装工程、需安装设备价值总额等按比例分摊。而土地征用费、地质勘察和建筑工程设计费等费用则按建筑工程造价比例分摊，生产工艺流程系统设计费按安装工程造价比例分摊。",{"id":6,"name":31,"category":13,"favorite":32},"建设工程计价",0]