[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899956":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899956,582,2,"多选题","根据《标准设计施工总承包招标文件》（2012年版），以下情形中，属于工程总承包价款调整原因的有（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","物价波动引起的价格调整",true,{"key":16,"text":17,"correct":14},"B","计日工引起的价格调整",{"key":19,"text":20,"correct":14},"C","暂估价引起的价格调整",{"key":22,"text":23,"correct":24},"D","监理人确定撤销变更意向书引起的价格调整",false,{"key":26,"text":27,"correct":14},"E","变更引起的价格调整","ABCE","2020版教材P274 总承包合同价款调整的主要原因包括变更，暂估价，计日工，暂列金额，物价波动以及法律法规的变化引起的价格调整 D选项，因为监理人确定撤销变更意向书，所以变更不成立，无价格调整。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]