[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899949":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899949,582,2,"多选题","采用工程量清单计价的工程，在办理建设工程结算时，工程量计算的原则和方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不符合质量要求的工程不予计量",true,{"key":16,"text":17,"correct":18},"B","只按工程量清单计量规范的要求进行计量",false,{"key":20,"text":21,"correct":18},"C","无论何种原因，超出合同工程范围的工程均不予计量",{"key":23,"text":24,"correct":14},"D","因承包人原因造成的返工的工程量，发包人不予计量",{"key":26,"text":27,"correct":14},"E","应按合同的约定对承包人完成合同工程的数量进行计算和确认","ADE","2020版教材P255 工程计量的原则包括下列三个方面：⑴不符合合同文件要求的工程不予计量。⑵按合同文件所规定的方法、范围、内容和单位计量。⑶因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人不予计量。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]