[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899945":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899945,582,2,"多选题","在合同履行过程中因不可抗力解除合同的价款结算与支付说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","由于不可抗力解除合同的，承包人应自行支付撤离现场所需的费用",false,{"key":16,"text":17,"correct":18},"B","发包人应向承包人支付已实施或部分实施的措施项目应付价款",true,{"key":20,"text":21,"correct":18},"C","发包人应向承包人支付承包人为合同工程合理订购且已交付的材料和工程设备货款",{"key":23,"text":24,"correct":18},"D","发包人一经支付材料和工程设备货款，则该材料和工程设备成为发包人的财产",{"key":26,"text":27,"correct":18},"E","发包人应向承包人支付承包人为完成合同工程而预期开支的任何合理费用","BCDE","2020版教材P261 《建设工程工程量清单计价规范》GB50500-2013第12.0.2条规定“发包人应向承包人支付承包人撤离现场所需的合理费用”。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]