[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899943":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899943,582,2,"多选题","发包人对工程质量有异议，竣工结算仍应按合同约定办理的情形有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程已竣工验收的",true,{"key":16,"text":17,"correct":14},"B","工程已竣工未验收，但实际投入使用的",{"key":19,"text":20,"correct":21},"C","工程已竣工未验收，且未实际投入使用的",false,{"key":23,"text":24,"correct":14},"D","工程停建，对无质量争议的部分",{"key":26,"text":27,"correct":21},"E","工程停建，对有质量争议的部分","ABD","2020版教材P260 （2）已竣工未验收且未实际投人使用的工程以及停工、停建工程的质量争议，双方应就有争议的部分委托有资质的检测鉴定机构进行检测，根据检测结果确定解决方案，或按工程质量监督机构的处理决定执行后办理竣工结算，无争议部分的竣工结算按合同约定办理。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]