[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899942":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899942,582,2,"多选题","采用双方约定争议调解人方式解决合同价款纠纷，其程序正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发承包双方可以在合同签订后共同约定争议调解人",true,{"key":16,"text":17,"correct":18},"B","发生争议，应由承包人将该争议以书面形式提交调解人，并将副本抄送发包人",false,{"key":20,"text":21,"correct":14},"C","调解人收到调解委托后28天内提出调解书",{"key":23,"text":24,"correct":14},"D","发承包双方接受调解书的，经双方签字后作为合同的补充文件",{"key":26,"text":27,"correct":18},"E","若发承包任一方对调解有异议，应在收到调解书14天内向另一方发出异议通知","ACD","2020版教材P265 “发承包双方应在合同中约定或在合同签订后共同约定争议调解人，负责双方在合同履行过程中发生争议的调解。如果发承包双方发生了争议，任何一方可以将该争议以书面形式提交调解人，并将副本抄送另一方，委托调解人调解。调解人应在收到调解委托后28天内，或由调解人建议并经发承包双方认可的其他期限内，提出调解书，发承包双方接受调解书的，经双方签字后作为合同的补充文件，对发承包双方具有约束力，双方都应立即遵照执行。如果发承包任一方对调解人的调解书有异议，应在收到调解书后28天内向另一方发出异议通知，并说明争议的事宜和理由。”",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]