[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899939":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899939,582,2,"多选题","工程量必须按照相关工程现行国家计量规范规定的工程量计算规则计算。以下说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人不予计量",true,{"key":16,"text":17,"correct":18},"B","规定单价合同、总价合同、成本加酬金合同适用一样的计量方法",false,{"key":20,"text":21,"correct":14},"C","成本加酬金合同按照单价合同的计量规定进行计量",{"key":23,"text":24,"correct":14},"D","单价合同若发现招标工程量清单中出现缺项、工程量偏差，或因工程变更引起工程量的增减，应按承包人在履行合同义务中完成的工程量计算",{"key":26,"text":27,"correct":14},"E","总价合同除按照工程变更规定引起的工程量增减外，总价合同各项目的工程量是承包人用于结算的最终工程量","ACDE","2020版教材P255 单价合同和总价合同规定不同的计量方法。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]