[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899938":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899938,582,2,"多选题","根据《标准施工招标文件》(2007年版)通用合同条款，承包人可能同时获得工期和费用补偿，但不能获得利润补偿的索赔事件有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人提供材料、工程设备不合格",false,{"key":16,"text":17,"correct":14},"B","发包人负责的材料延迟提供",{"key":19,"text":20,"correct":14},"C","迟延提供施工场地",{"key":22,"text":23,"correct":24},"D","施工中发现文物",true,{"key":26,"text":27,"correct":24},"E","施工中遇到不利物质条件","DE","根据《标准施工招标文件》，选项ABC可索赔工期+费用+利润；选项DE能索赔工期+费用。2020教材P245-253",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]