[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899937":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899937,582,2,"多选题","根据《标准施工招标文件》的规定，承包人只能获得“工期+费用”补偿的事件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基准日后法律的变化",false,{"key":16,"text":17,"correct":18},"B","施工中发现文物、古迹",true,{"key":20,"text":21,"correct":14},"C","发包人提供的材料、工程设备造成工程质量不合格",{"key":23,"text":24,"correct":18},"D","施工中遇到不利的物质条件",{"key":26,"text":27,"correct":14},"E","因发包人原因导致承包人工程返工","BD","根据《标准施工招标文件》，选项A可索赔费用；选项BD可索赔工期+费用；选项CE可索赔工期+费用+利润。2020教材P245-253",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]