[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899935":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899935,582,2,"多选题","某施工合同约定，现场主导施工机械一台，由承包人租得，台班单价为200元／台班，租赁费100元／天，人工工资为50元／工日，窝工补贴20元／工日，以人工费和机械费为基数的综合费率为30％。在施工过程中，发生了如下事件：①遇异常恶劣天气导致停工2天，人员窝工30工日，机械窝工2天；②发包人增加合同工作，用工20工日，使用机械1台班；③场外大范围停电致停工1天，人员窝工20工日，机械窝工1天。据此，下列选项正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","因异常恶劣天气停工可得的费用索赔额为800元",false,{"key":16,"text":17,"correct":14},"B","因异常恶劣天气停工可得的费用索赔额为1040元",{"key":19,"text":20,"correct":21},"C","因发包人增加合同工作，承包人可得的费用索赔额为1560元",true,{"key":23,"text":24,"correct":21},"D","因停电所致停工，承包人可得的费用索赔额为500元",{"key":26,"text":27,"correct":14},"E","承包人可得的总索赔费用为2500元","CD","事件①不能获得费用索赔 ； 事件②索赔额=(20×50+1×200)×(1+30％)=1560(元)； 事件③索赔额=20×20+1×100=500(元)； 索赔额合计=2060(元)。 2020教材P245-253",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]