[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899930":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899930,582,2,"多选题","根据《建设工程工程量清单计价规范》GB 50500-2013，关于计日工费用的确认和支付，下列说法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人应按照确认的计日工现场签证报告核实该类项目的工程数量和单价",false,{"key":16,"text":17,"correct":18},"B","已标价工程量清单中有该类计日工单价的，按该单价计算",true,{"key":20,"text":21,"correct":14},"C","已标价工程量清单中没有该类计日工单价的，按承包人报价计算",{"key":23,"text":24,"correct":18},"D","计日工价款应列入同期进度款支付",{"key":26,"text":27,"correct":18},"E","发包人通知承包人以计日工方式实施的零星工作，承包人应予执行","BDE","2020版教材P240 2.计日工费用的确认和支付任一计日工项目实施结束。承包人应按照确认的计日工现场签证报告核实该类项目的工程数量，并根据核实的工程数量和承包人已标价工程量清单中的计日工单价计算，提出应付价款；已标价工程量清单中没有该类计日工单价的，由发承包双方按工程变更的有关的规定商定计日工单价计算。.每个支付期末，承包人应与进度款同期向发包人提交本期间所有计日工记录的签证汇总表，以说明本期间自己认为有权得到的计日工金额，调整合同价款，列入进度款支付。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]