[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899929":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899929,582,2,"多选题","下列关于现场签证的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工中遇到不利物质条件，承包商可提出现场签证",true,{"key":16,"text":17,"correct":18},"B","施工中遇到法律法规变化，承包商可提出现场签证",false,{"key":20,"text":21,"correct":14},"C","承包商被要求完成合同以外的零星项目，可提出现场签证",{"key":23,"text":24,"correct":14},"D","施工中合同工程内容与发包人要求不一致时，承包商可提出现场签证",{"key":26,"text":27,"correct":18},"E","现场签证工作完成7天后，承包人按现场签证内容计算价款，确认后作为增加合同价款","ACD","2020版教材P253 本题考查的是其他类合同价款调整事项 “现场签证的提出包括下列内容：承包人应发包人要求完成合同以外的零星项目、非承包人责任事件等工作的，发包人应及时以书面形式向承包人发出指令，提供所需的相关资料；承包人在收到指令后，应及时向发包人提出现场签证要求。”",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]