[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899925":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899925,582,2,"多选题","下列事件的发生，已经或将造成工期延误，则按照《标准施工招标文件》中相关合同条件，可以获得工期补偿的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","延迟提供图纸",true,{"key":16,"text":17,"correct":18},"B","监理人对已覆盖的隐蔽工程要求重新检查且检查结果不合格",false,{"key":20,"text":21,"correct":18},"C","承包人的设备故障",{"key":23,"text":24,"correct":14},"D","发包人提供工程设备不合格",{"key":26,"text":27,"correct":14},"E","异常恶劣的气候条件","ADE","2020版教材P247 标准施工招标文件文件中",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]