[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899924":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899924,582,2,"多选题","以下有关提前竣工的说法正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人应当依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20％，超过的，应在招标文件中明示增加赶工费用",true,{"key":16,"text":17,"correct":14},"B","约定提前竣工奖励的，如果承包人的实际竣工日期早于计划竣工日期，承包人有权向发包人提出并得到提前竣工天数和合同约定的每日历天应奖励额度的乘积计算的提前竣工奖励",{"key":19,"text":20,"correct":14},"C","双方应当在合同中约定提前竣工奖励的最高限额",{"key":22,"text":23,"correct":24},"D","发包人要求合同工程提前竣工，发包人无须征得承包人同意",false,{"key":26,"text":27,"correct":14},"E","发包人要求合同工程提前竣工，发包人应承担承包人由此增加的赶工费","ABCE","2020版教材P245 发包人要求合同工程提前竣工，应征得承包人同意后与承包人商定采取加快工 程进度的措施，并修订合同工程进度计划。发包人应承担承包人由此增加的赶工费。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]