[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899918":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899918,582,2,"多选题","在工程总承包投标报价分析中，工程总承包项目的成本费用按阶段可以分解成（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","勘察费用",true,{"key":16,"text":17,"correct":14},"B","设计费用",{"key":19,"text":20,"correct":14},"C","采购费用",{"key":22,"text":23,"correct":14},"D","施工费用",{"key":25,"text":26,"correct":27},"E","其他费用",false,"ABCD","2020版教材P225 工程总承包项目的成本费用由施工费用，直接设备材料费用，分包合同费用，公司本部费用，调试、开车服务费用和其他费用组成，也可以将工程总承包费用按阶段分解成勘察设计费用、采购费用和施工费用三部分。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]