[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899894":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899894,582,2,"多选题","当编制招标工程量清单时，需要合理考虑施工顺序，通常需要考虑的内容包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工进度计划要满足合同对工期的要求",false,{"key":16,"text":17,"correct":18},"B","各分部分项工程之间的关系",true,{"key":20,"text":21,"correct":18},"C","当地的气候条件和水文要求",{"key":23,"text":24,"correct":14},"D","现场的平面布置及各种技术措施",{"key":26,"text":27,"correct":18},"E","施工方法和施工机械的要求","BCE","当编制招标工程量清单时需要拟订常规施工组织设计，在合理确定施工顺序时需要考虑以下几点：各分部分项工程之间的关系、施工方法和施工机械的要求、当地的气候条件和水文要求、施工顺序对工期的影响。2020教材P184-190",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]