[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899892":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899892,582,2,"多选题","在分部分项工程量清单编制计算工程量时，应依据的计算原则包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","计算口径一致",true,{"key":16,"text":17,"correct":14},"B","按工程量计算规则计算",{"key":19,"text":20,"correct":14},"C","按图纸计算",{"key":22,"text":23,"correct":14},"D","按一定顺序计算",{"key":25,"text":26,"correct":27},"E","根据工程内容和定额项目计算",false,"ABCD","2020版教材P187 分部分项工程量清单编制中，必须依据的一定的计算原则及方法：（1）计算口径一致；（2）按工程量计算规则计算；（3）按图纸计算；（4）按一定顺序计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]