[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899888":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899888,582,2,"多选题","下列关于招标工程量清单的描述，说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","招标工程量清单是招标文件的组成部分，可以由招标人委托的工程造价咨询人编制",true,{"key":16,"text":17,"correct":14},"B","招标人对工程量清单中各分部分项工程工程量的准确性和完整性负责",{"key":19,"text":20,"correct":21},"C","由于措施项目投标人可自行选择，因此招标人无须对措施项目工程量的准确性和完整性负责",false,{"key":23,"text":24,"correct":14},"D","招标工程量清单编制前也要进行现场踏勘",{"key":26,"text":27,"correct":21},"E","招标工程量清单编制时需进行先进施工组织设计方案的编制，以提高施工水平","ABD","2020版教材P184 C错误，招标人对工程量清单中各分部分项工程或适合以分部分项工程项目清单设置的措施项目的工程量的准确性和完整性负责； E错误，招标工程量清单编制的准备工作（1）初步研究（2）现场踏勘（3）拟定常规施工组织设计。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]