[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899887":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899887,582,2,"多选题","根据《建设工程工程量清单计价规范》GB50500—2013，招标控制价中综合单价中应考虑的风险因素包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目管理的复杂性",true,{"key":16,"text":17,"correct":14},"B","项目的技术难度",{"key":19,"text":20,"correct":21},"C","人工单价的市场变化",false,{"key":23,"text":24,"correct":14},"D","材料价格的市场风险",{"key":26,"text":27,"correct":21},"E","税金、规费的政策变化","ABD","2020版教材P194 在招标文件中应通过预留一定的风险费用，或明确说明风险所包括的范围及超出该范围的价格调整方法。对于招标文件中未做要求的可按以下原则确定：⑴对于技术难度较大和管理复杂的项目，可考虑一定的风险费用，并纳入到综合单价中。⑵对于工程设备、材料价格的市场风险，应依据招标文件的规定，工程所在地或行业工程造价管理机构的有关规定，以及市场价格趋势考虑一定率值的风险费用，纳入到综合单价中。⑶税金、规费等法律、法规、规章和政策变化的风险和人工单价等风险费用不应纳入综合单价。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]