[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899861":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899861,582,2,"多选题","关于工业建设项目的设备选用，其选用的重点因设计形式的不同而不同，应选择能满足（ ）要求的最适用的设备和机械。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建设规模",false,{"key":16,"text":17,"correct":14},"B","建筑结构",{"key":19,"text":20,"correct":21},"C","生产工艺",true,{"key":23,"text":24,"correct":21},"D","生产能力",{"key":26,"text":27,"correct":14},"E","环保措施","CD","2020版教材P150 关于工业建设项目的设备选用，其选用的重点因设计形式的不同而不同，应选择能满足生产工艺和生产能力要求的最适用的设备和机械。建设规模、环保措施属于工艺设计阶段影响工程造价的因素。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]