[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899854":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899854,582,2,"多选题","下列费用中，项目投产时将直接形成固定资产的费用有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建设单位管理费",true,{"key":16,"text":17,"correct":14},"B","研究试验费",{"key":19,"text":20,"correct":21},"C","生产准备费",false,{"key":23,"text":24,"correct":14},"D","工程保险费",{"key":26,"text":27,"correct":14},"E","临时设施费","ABDE","2020版教材P142 建设投资由形成固定资产的费用、形成无形资产的费用、形成其他资产的费用和预备费四部分组成。固定资产费用是指项目投产时将直接形成固定资产的建设投资，包括工程费用和工程建设其他费用中按规定将形成固定资产的费用，后者被称为固定资产其他费用，主要包括建设管理费、可行性研究费、研究试验费、勘察设计费、环境影响评价费、场地准备及临时设施费、引进技术和引进设备其他费、工程保险费、联合试运转费、特殊设备安全监督检验费和市政公用设施建设及绿化费等。生产准备费属于其他资产费用的范畴。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]