[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899852":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899852,582,2,"多选题","项目决策阶段进行设备选用时，应处理好的问题包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进口设备与国产设备费用的比例关系问题",false,{"key":16,"text":17,"correct":18},"B","进口设备的备件供应与维修能力问题",true,{"key":20,"text":21,"correct":18},"C","设备间的衔接配套问题",{"key":23,"text":24,"correct":18},"D","设备与原有厂房之间的配套问题",{"key":26,"text":27,"correct":18},"E","进口设备与原材料之间的配套问题","BCDE","2020版教材P125 设备选用应注意处理的问题：①要尽量选用国产设备；②要注意进口设备之间以及国内外设备之间的衔接配套问题；③要注意进口设备与原有国产设备、厂房之间的配套问题；④要注意进口设备与原材料、备品备件及维修能力之间的配套问题。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]