[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899851":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899851,582,2,"多选题","项目规模确定中需考虑的主要环境因素包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","产业政策",true,{"key":16,"text":17,"correct":14},"B","协作及土地条件",{"key":19,"text":20,"correct":21},"C","劳动力市场情况",false,{"key":23,"text":24,"correct":14},"D","运输通信条件",{"key":26,"text":27,"correct":21},"E","竞争对手状况","ABD","2020版教材P120 需要考虑的主要环境因素有：政策因素，燃料动力供应，协作及土地条件，运输及通信条件。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]