[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899837":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899837,582,2,"多选题","下列关于制约项目建设规模合理化因素的表述中，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","确定项目生产规模的前提是项目资金供应情况",false,{"key":16,"text":17,"correct":14},"B","先进适用的生产技术及技术装备是项目规模效益实现的保证",{"key":19,"text":20,"correct":21},"C","市场价格分析是制定营销策略和影响竞争力的主要因素",true,{"key":23,"text":24,"correct":21},"D","原材料市场、资金市场和劳动力市场对项目规模的选择起到制约作用",{"key":26,"text":27,"correct":21},"E","市场风险分析是确定项目建设规模的重要依据","CDE","2020版教材P120 选项A错误，确定项目生产规模的前提是市场需求；选项B错误，效益实现的保证并非先进适用的生产技术及技术装备，应当是管理技术水平。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]