[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899835":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899835,582,2,"多选题","下列各项内容中属于机械台班幅度差的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","正常施工条件下，机械在施工中不可避免的工序间歇",true,{"key":16,"text":17,"correct":18},"B","工人进行准备与结束工作时，机器停止工作而引起的中断时间",false,{"key":20,"text":21,"correct":14},"C","工程开工或收尾时工作量不饱满所损失的时间",{"key":23,"text":24,"correct":14},"D","检查工程质量影响机械操作的时间",{"key":26,"text":27,"correct":14},"E","机械维修引起的停歇时间","ACDE","本题考查的是预算定额及其基价编制。 机械幅度差包括：(1)施工机械转移工作面及配套机械相互影响损失的时间；(2)正常施工条件下，机械在施工中不可避免的工序间歇；(3)工程开工或收尾时工作量不饱满所损失的时间；(4)检查工程质量影响机械操作的时间；(5)临时停机、停电影响机械操作的时间；(6)机械维修引起的停歇时间。2020教材P76-84",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]