[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899833":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899833,582,2,"多选题","下列属于预算定额机械台班消耗量中机械幅度差的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","施工机械转移工作面及配套机械相互影响损失的时间",true,{"key":16,"text":17,"correct":14},"B","机械维修引起的停歇时间",{"key":19,"text":20,"correct":14},"C","工程收尾时工作量不饱满造成的机械停歇时间",{"key":22,"text":23,"correct":14},"D","在正常施工条件下，机械在施工中不可避免的工序间歇时间",{"key":25,"text":26,"correct":27},"E","运输车辆在装货和卸货时的停车时间",false,"ABCD","2020版教材P79 机械台班幅度差一般包括：施工机械转移及配套机械相互影响损失的时间；在正常施工条件下，机械在施工中不可避免的工序间歇；工程收尾和工程量不饱满造成的机械停歇时间；因检查工程质量造成的机械停歇的时间；临时停机、停电影响机械操作的时间；机械维修引起的停歇时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]