[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899832":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899832,582,2,"多选题","下列与施工机械工作相关的时间中，应包括在预算定额机械台班消耗量中，但不包括在施工定额中的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","低负荷下工作时间",false,{"key":16,"text":17,"correct":18},"B","正常施工时机械施工不可避免的工序间歇",true,{"key":20,"text":21,"correct":18},"C","机械维修引起的停歇时间",{"key":23,"text":24,"correct":18},"D","开工时工作量不饱满所损失的时间",{"key":26,"text":27,"correct":14},"E","不可避免的中断时间","BCD","2020版教材P79 机械台班幅度差是指在施工定额中所规定的范围内没有包括，而在实际施工中又不可避免产生的影响机械或使机械停歇的时间。其内容包括：（1）施工机械转移工作面及配套机械相互影响损失的时间。（2）在正常施工条件下，机械在施工中不可避免的工序间歇。（3）工程开工或收尾时工作量不饱满所损失的时间。（4）检查工程质量影响机械操作的时间。（5）临时停机、停电影响机械操作的时间。（6）机械维修引起的停歇时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]