[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899823":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899823,582,2,"多选题","下列施工机械的停歇时间，在预算定额机械幅度差中考虑的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","机械维修引起的停歇",true,{"key":16,"text":17,"correct":14},"B","工程质量检查引起的停歇",{"key":19,"text":20,"correct":14},"C","机械转移工作面引起的停歇",{"key":22,"text":23,"correct":24},"D","进行准备与结束工作时间引起的停歇",false,{"key":26,"text":27,"correct":24},"E","施工机械在单位工程之间转移引起的停歇","ABC","2020版教材P79 机械台班幅度差是指在施工定额中所规定的范围内没有包括，而在实际施工中又不可避免产的影响机械或使机械停歇的时间，其内容包括：（1）施工机械转移工作面及配套机械相互影响损失的时间；（2）在正常施工条件中，机械在施工中不可避免的工序停歇；（3）工程开工或收尾时工程量不饱满所损失的时间；（4）检查工程质量影响机械操作的时间；（5）临时停机、停电影响机械操作的时间；（6）机械维修引起的停歇时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]