[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899822":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899822,582,2,"多选题","确定预算定额人工工日消耗量过程中，应计入其他用工的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","材料二次搬运用工",false,{"key":16,"text":17,"correct":18},"B","电焊点火用工",true,{"key":20,"text":21,"correct":14},"C","按劳动定额规定应增（减）计算的用工",{"key":23,"text":24,"correct":18},"D","临时水电线路移动造成的停工",{"key":26,"text":27,"correct":14},"E","完成某一分项工程所需消耗的技术工种用工","BD","2020版教材P78 （2）其他用工。其他用工是辅助基本用工消耗的工日，包括超运距用工、辅助用工和人工幅度差用工。 基本用工包括.1）完成定额计量单位的主要用工；2）按劳动定额规定应增（减）计算的用工量。 基本用工指完成一定计量单位的分项工程或结构构件的各项工作过程的施工任务所必需消耗的技术工种用工。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]