[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899806":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899806,582,2,"多选题","下列各类时间中属于工序作业时间的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","基本工作时间",true,{"key":16,"text":17,"correct":14},"B","辅助工作时间",{"key":19,"text":20,"correct":21},"C","准备与结束工作时间",false,{"key":23,"text":24,"correct":21},"D","不可避免的中断时间",{"key":26,"text":27,"correct":21},"E","休息时间","AB","本题考查的是确定人工定额消耗量的基本方法。 根据计时观察资料的分析和选择，我们可以获得各种产品的基本工作时间和辅助工作时间，将这两种时间合并，可以称之为工序作业时间。2020教材P61-63",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]