[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899804":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899804,582,2,"多选题","在人工定额的编制过程中，通常可以采用工时规范或经验数据来确定的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基本工作时间",false,{"key":16,"text":17,"correct":18},"B","辅助工作时间",true,{"key":20,"text":21,"correct":18},"C","准备与结束时间",{"key":23,"text":24,"correct":18},"D","不可避免的中断时间",{"key":26,"text":27,"correct":18},"E","休息时间","BCDE","2020版教材P62 辅助工作时间的确定方法与基本工作时间相同。如果在计时观察时不能取得足够的资料，也可采用工时规范或经验数据来确定；如果在记时观察资料中不能取得足够的准备与结束时间的资料，也可根据工时规范或经验数据来确定；不可避免中断时间也需要根据测时资料通过整理分析获得，也可以根据经验数据或工时规范，以占工作日的百分比表示此项工时消耗的时间定额；规范时间均可利用工时规范或经验数据确定。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]