[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899803":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899803,582,2,"多选题","下列施工工作的时间分类选项中，属于工人有效工作时间的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基本工作时间",true,{"key":16,"text":17,"correct":18},"B","休息时间",false,{"key":20,"text":21,"correct":14},"C","辅助工作时间",{"key":23,"text":24,"correct":14},"D","准备与结束工作时间",{"key":26,"text":27,"correct":18},"E","不可避免的中断时间","ACD","2020版教材P56 有效工作时间是从生产效果来看与产品生产直接有关的时间消耗。其中包括基本工作时间、辅助工作时间、准备与结束工作时间的消耗。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]