[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899802":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899802,582,2,"多选题","下列工人工作时间中，虽属于损失时间，但在拟定定额时又要适度考虑它的影响的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工本身导致的停工时间",false,{"key":16,"text":17,"correct":18},"B","非施工本身导致的停工时间",true,{"key":20,"text":21,"correct":14},"C","不可避免的中断时间",{"key":23,"text":24,"correct":14},"D","多余工作时",{"key":26,"text":27,"correct":18},"E","偶然工作时间","BE","2020版教材P57 本题考查的是工作时间消耗的相关内容。 在损失时间中，由于偶然工作能获得一定产品，拟定定额时要适当考虑它的影响。非施工本身造成的停工时间，是由于水源、电源中断引起的停工时间，定额中应给予合理的考虑。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]