[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899800":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899800,582,2,"多选题","当确定测时法的观察次数时，需要重点考虑的因素是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","同时测定施工过程的类型数",false,{"key":16,"text":17,"correct":18},"B","要求的算术平均值精确度",true,{"key":20,"text":21,"correct":14},"C","被测定的工人人数",{"key":23,"text":24,"correct":18},"D","数列的稳定系数",{"key":26,"text":27,"correct":14},"E","完成产品的可能次数等","BD","2020版教材P59 测时法中，需要的观察次数与要求的算术平均值精确度及数列的稳定系数有关，而A、C、E答案均为写实记录法所需的延续时间的确定因素。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]