[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899798":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899798,582,2,"多选题","确定施工时间定额时，下列工人工作时间可以计入定额时间的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","机手并动下的辅助工作时间",false,{"key":16,"text":17,"correct":18},"B","准备与结束工作的时间",true,{"key":20,"text":21,"correct":18},"C","与施工过程工艺特点有关的工作中断时间",{"key":23,"text":24,"correct":18},"D","必需的休息时间",{"key":26,"text":27,"correct":14},"E","施工本身造成的停工时间","BCD","2020版教材P56 工人工作时间分为必需消耗的时间和损失时间。编制定额时，必需消耗的时间计入定额，损失时间不能计入定额（偶然工作时间和非承包商原因的停工损失时间可给予适当考虑），本题中施工本身造成的停工时间属于损失时间，机手并动下的辅助工作时间计入机械运转，其他属于必需消耗的时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]