[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899795":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899795,582,2,"多选题","工人工作时间中的损失时间包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","准备与结束工作时间",false,{"key":16,"text":17,"correct":18},"B","施工本身造成的停工时间",true,{"key":20,"text":21,"correct":18},"C","非施工本身造成的停工时间",{"key":23,"text":24,"correct":14},"D","休息时间",{"key":26,"text":27,"correct":18},"E","偶然工作时间","BCE","2020版教材P56 工人工作时间可以分为必需消耗的时间和损失时间两类，其中损失时间包括多余和偶然工作时间、停工时间和违背劳动纪律所引起的工时损失，停工时间包括施工本身造成的停工时间和非施工本身造成的停工时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]