[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899789":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899789,582,2,"多选题","分部分项工程量清单的项目特征应按“清单计价规范”附录中规定的项目特征，结合()予以详细而准确的表述和说明。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","技术规范",true,{"key":16,"text":17,"correct":18},"B","工程内容",false,{"key":20,"text":21,"correct":14},"C","标准图集",{"key":23,"text":24,"correct":14},"D","施工图纸",{"key":26,"text":27,"correct":14},"E","安装位置","ACDE","分部分项工程项目清单的项目特征应按各专业工程工程量计算规范附录中规定的项目特征，结合技术规范、标准图集、施工图纸，按照工程结构、使用材质及规格或安装位置等，予以详细而准确的表述和说明. 2020教材P44-47",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]