[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899787":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899787,582,2,"多选题","对于适用于以“项”计价的措施项目，其计算基础可为( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","定额基价",false,{"key":16,"text":17,"correct":14},"B","定额人工费+定额材料费",{"key":19,"text":20,"correct":14},"C","定额机械费",{"key":22,"text":23,"correct":24},"D","定额人工费",true,{"key":26,"text":27,"correct":24},"E","定额人工费+定额机械费","DE","安全文明施工费的计算基础可为“定额基价”、“定额人工费”或“定额人工费+定额施工机具使用费”，其他以“项”基价的措施项目的计算基础可为“定额人工费”或“定额人工费+定额施工机具使用费”。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]