[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899784":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899784,582,2,"多选题","关于工程量清单编制中的项目特征描述，下列说法中正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","措施项目无需描述项目特征",false,{"key":16,"text":17,"correct":18},"B","应按计量规范附录中规定的项目特征，结合技术规范、标准图集加以描述",true,{"key":20,"text":21,"correct":14},"C","对完成清单项目可能发生的具体工作和操作程序仍需加以描述",{"key":23,"text":24,"correct":14},"D","图纸中已有的工程规格、型号、材质等可不描述",{"key":26,"text":27,"correct":18},"E","项目独有的特征，清单编制人视项目具体情况确定","BE","2020版教材P45 “分部分项工程项目清单的项目特征应按各专业工程工程量计算规范附录中规定的项目特征，结合技术规范、标准图集、施工图纸，按照工程结构、使用材质及规格或安装位置等，予以详细而准确的表述和说明。凡项目特征中未描述到的其他独有特征，由清单编制人视项目具体情况确定，以准确描述清单项目为准。”",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]