[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899781":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899781,582,2,"多选题","措施项目清单的编制依据有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工现场情况",true,{"key":16,"text":17,"correct":14},"B","工程特点",{"key":19,"text":20,"correct":21},"C","施工承包合同",false,{"key":23,"text":24,"correct":14},"D","常规施工方案",{"key":26,"text":27,"correct":14},"E","建设工程设计文件","ABDE","2020版教材P48 措施项目清单的编制依据包括以下五个方面： （1）施工现场情况、地勘水文资料、工程特点。 （2）常规施工方案。 （3）与建设工程有关的标准、规范、技术资料。 （4）拟定招标文件。 （5）建设工程设计文件及相关资料。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]