[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899774":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899774,582,2,"多选题","关于措施项目清单编制依据，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","拟定的招标文件",true,{"key":16,"text":17,"correct":18},"B","其他项目清单",false,{"key":20,"text":21,"correct":14},"C","常规施工方案",{"key":23,"text":24,"correct":14},"D","与建设工程有关的标准、规范",{"key":26,"text":27,"correct":18},"E","相关法律法规","ACD","2020版教材P48 本题考查的是措施项目清单的编制依据。措施项目清单的编制依据主要有：（1）施工现场情况、地勘水文资料、工程特点；（2）常规施工方案；（3）与建设工程有关的标准、规范、技术资料；（4）拟定的招标文件；（5）建设工程设计文件及相关资料。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]