[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899771":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899771,582,2,"多选题","下列措施项目中，应按分部分项工程量清单编制方式编制的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","超高施工增加",true,{"key":16,"text":17,"correct":18},"B","建筑物的临时保护设施",false,{"key":20,"text":21,"correct":14},"C","大型机械设备进出场及安拆",{"key":23,"text":24,"correct":18},"D","已完工程及设备保护",{"key":26,"text":27,"correct":14},"E","施工排水、降水","ACE","2020版教材P47 有些措施项目时可以计算工程量的项目，如脚手架工程，混凝土模板及支架（撑），垂直运输、超高施工增加，大型机械设备进出场及安拆，施工排水、降水等，这类措施项目按照分部分项工程量清单的方式采用综合单价计价，更有利于措施费的确定和调整。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]